Weather delay tool
Weather record

Construction weather in York, April 2026

Daily rainfall, frost and wind for York against the 10-year average — the starting point for any weather delay conversation on site.

Weather delay record

York — 1 Apr 2026 to 30 Apr 2026

YO1 8QG · 1 Apr 202630 Apr 2026

Daily record

DateRain (mm)Min °CMax °CGust (mph)Flags
1 Apr 20260.27.312.824
2 Apr 20260.13.210.521
3 Apr 20261.56.315.644
4 Apr 20261.13.715.051wind
5 Apr 20260.44.510.347wind
6 Apr 20260.01.713.221
7 Apr 20260.03.516.726
8 Apr 20260.06.419.416
9 Apr 20260.45.214.032
10 Apr 20260.03.611.024
11 Apr 20261.96.511.037
12 Apr 20263.95.012.440
13 Apr 20260.51.112.715
14 Apr 20261.21.615.328
15 Apr 20266.59.217.237wet
16 Apr 20260.28.614.931
17 Apr 20261.59.014.930
18 Apr 20260.77.113.630
19 Apr 20260.03.512.218
20 Apr 20260.82.912.219
21 Apr 20260.04.912.834
22 Apr 20260.04.712.928
23 Apr 20260.02.314.015
24 Apr 20260.00.815.911
25 Apr 20260.02.217.423
26 Apr 20260.03.316.919
27 Apr 20260.88.317.327
28 Apr 20260.06.012.526
29 Apr 20260.04.715.128
30 Apr 20260.06.518.028

1 day with rainfall over 5 mm in this period.

Data: ERA5 reanalysis via Open-Meteo, taken at the nearest model grid point to the postcode — not a Met Office station record. Baselines are the mean of the same calendar months over the previous 10 years at this location. Whether conditions meet a contractual test (e.g. JCT “exceptionally adverse weather” or an NEC 1-in-10-year event) is a matter for the contract — this is a factual weather record, not advice.