Programme template

Barn conversion: typically 2434 weeks.

Conversion of an agricultural barn to a dwelling — structural repair, new envelope performance, full services.

Durations are typical ranges for a well-run job with normal lead times — actual programmes vary with site conditions, weather and procurement.

Stage-by-stage

  1. Site set-up & protection3–5 days
  2. Strip-out & structural survey confirmationBat/ecology conditions often constrain start dates5–8 days
  3. Structural repairs & underpinningThe big unknown in any barn — allow contingency10–20 days
  4. BC: structural inspectioninspection / milestone
  5. New openings & steel frames6–10 days
  6. Roof repairs & insulation build-up10–15 days
  7. New floor slab & DPM6–9 days
  8. BC: DPC/slab inspectioninspection / milestone
  9. Glazing & external doorsBespoke glazing for barn openings: long lead times4–6 days
  10. Internal framing & insulation8–12 days
  11. First fix & new services connectionsOff-mains drainage/treatment plant adds time if needed8–12 days
  12. Plastering & drying10–15 days
  13. Second fix, kitchen & bathrooms12–16 days
  14. Decoration & floors8–12 days
  15. External works & drainage6–10 days
  16. Snagging & completion3–5 days
  17. BC: completion certificateinspection / milestone

Customise this programme:

Residential

Commercial

Packages

Typical durations for a well-run job — actual programmes vary with site, weather and lead times.

Adjust stage durations
Completed In Progress Upcoming

Turn this into a live tracked project — weekly updates, photos and RAG status your client can follow. Track this build live — free