All programme templates
Programme template

Full house refurbishment: typically 1420 weeks.

Whole-house strip-out and refurbishment: rewire, replumb, new kitchen and bathrooms, decoration throughout.

Durations are typical ranges for a well-run job with normal lead times — actual programmes vary with site conditions, weather and procurement.

Stage-by-stage

  1. Strip-out & site set-up5–8 days
  2. Structural alterations & steels5–10 days
  3. BC: structural inspectioninspection / milestone
  4. Damp-proofing & timber treatment3–5 days
  5. Full rewire — first fix5–8 days
  6. Replumb & heating — first fix5–8 days
  7. Carpentry first fix & insulation4–6 days
  8. Plastering throughout8–12 days
  9. Plaster drying7–12 days
  10. Second fix: electrics, plumbing, joinery8–12 days
  11. Kitchen installation5–8 days
  12. Bathroom installation5–8 days
  13. Decoration throughout8–12 days
  14. Flooring & carpets3–5 days
  15. Snagging & deep clean3–5 days

Customise this programme:

Residential

Commercial

Packages

Typical durations for a well-run job — actual programmes vary with site, weather and lead times.

Adjust stage durations
Completed In Progress Upcoming