All programme templates
Programme template

Small residential development (2–6 plots): typically 4060 weeks.

Small housing development built in sequence with overlapping plots — groundworks through to sales handovers.

Durations are typical ranges for a well-run job with normal lead times — actual programmes vary with site conditions, weather and procurement.

Stage-by-stage

  1. Site establishment & compound8–12 days
  2. Bulk earthworks & site drainage10–20 days
  3. Road & services infrastructureUtility company lead times drive this — apply early15–25 days
  4. Plot foundations (rolling)20–30 days
  5. BC: foundations sign-offs (per plot)inspection / milestone
  6. Superstructures (rolling)40–60 days
  7. Roofs & watertight (rolling)25–35 days
  8. First fix (rolling)25–35 days
  9. Plastering & drying (rolling)20–30 days
  10. Second fix & finishes (rolling)30–40 days
  11. External works & landscaping15–25 days
  12. Show plot completeinspection / milestone
  13. Snagging & plot handovers10–20 days
  14. Final completionsinspection / milestone

Customise this programme:

Residential

Commercial

Packages

Typical durations for a well-run job — actual programmes vary with site, weather and lead times.

Adjust stage durations
Completed In Progress Upcoming

Turn this into a live tracked project — weekly updates, photos and RAG status your client can follow. Track this build live — free