Programme template

Groundworks & external works package: typically 814 weeks.

Groundworks subcontract package: reduce dig, foundations, drainage, slabs and external finishes for a main contractor.

Durations are typical ranges for a well-run job with normal lead times — actual programmes vary with site conditions, weather and procurement.

Stage-by-stage

  1. Mobilisation & site set-up2–4 days
  2. Reduce dig & muck awayMuck-away costs balloon if ground is worse than the SI — flag early4–8 days
  3. Foundations & concrete6–10 days
  4. Foundations sign-offinspection / milestone
  5. Below-ground drainage5–8 days
  6. Drainage test & sign-offinspection / milestone
  7. Sub-base & floor slabs5–8 days
  8. Service ducts & external drainage4–6 days
  9. Kerbs, paths & hardstandings5–8 days
  10. Topsoil, landscaping & fencing3–6 days
  11. Demobilise & handover1–2 days

Customise this programme:

Residential

Commercial

Packages

Typical durations for a well-run job — actual programmes vary with site, weather and lead times.

Adjust stage durations
Completed In Progress Upcoming

Turn this into a live tracked project — weekly updates, photos and RAG status your client can follow. Track this build live — free