Programme template

Industrial unit / portal-frame shell: typically 2028 weeks.

Steel portal-frame industrial unit to weathertight shell with office pod: groundworks, frame, envelope, services.

Durations are typical ranges for a well-run job with normal lead times — actual programmes vary with site conditions, weather and procurement.

Stage-by-stage

  1. Site establishment & earthworks8–12 days
  2. Foundations & pad bases10–15 days
  3. BC: foundations inspectioninspection / milestone
  4. Drainage & external services8–12 days
  5. Steel frame erectionSteel fabrication lead 6–10 weeks from order — programme driver8–12 days
  6. Frame completeinspection / milestone
  7. Roof & wall claddingCladding is wind-speed limited — winter float advised10–15 days
  8. Floor slab & power float5–8 days
  9. Weathertightinspection / milestone
  10. Office pod construction10–15 days
  11. M&E installation10–15 days
  12. Dock doors, level access & external hardstanding8–12 days
  13. Commissioning & certification4–6 days
  14. Snagging & handover3–5 days
  15. Practical completioninspection / milestone

Customise this programme:

Residential

Commercial

Packages

Typical durations for a well-run job — actual programmes vary with site, weather and lead times.

Adjust stage durations
Completed In Progress Upcoming

Turn this into a live tracked project — weekly updates, photos and RAG status your client can follow. Track this build live — free