Programme template

Retail unit fit-out: typically 812 weeks.

Shell-to-trading fit-out of a high-street or retail-park unit: shopfront, services, finishes, merchandising.

Durations are typical ranges for a well-run job with normal lead times — actual programmes vary with site conditions, weather and procurement.

Stage-by-stage

  1. Site set-up & hoarding2–3 days
  2. Strip-out & survey3–5 days
  3. Shopfront & entrance worksShopfront fabrication lead 4–8 weeks; planning may apply5–10 days
  4. Partitions, back-of-house & WCs5–8 days
  5. M&E first fix5–8 days
  6. Ceilings & lighting4–6 days
  7. Wall & floor finishes5–8 days
  8. M&E second fix & commissioning3–5 days
  9. Shopfitting & fixtures5–8 days
  10. Merchandising & staff training2–4 days
  11. Snagging & clean2–3 days
  12. Store openinginspection / milestone

Customise this programme:

Residential

Commercial

Packages

Typical durations for a well-run job — actual programmes vary with site, weather and lead times.

Adjust stage durations
Completed In Progress Upcoming

Turn this into a live tracked project — weekly updates, photos and RAG status your client can follow. Track this build live — free