Schedule
Budget
Risk
Overall
Overall Progress
55%Programme Timeline
Nov 2025 — Aug 2026Enabling & Demolition
Substructure
Superstructure Frame
Envelope & Cladding
M&E Services
Fit-out & Handover
Practical Completion
Key Dates
Latest Update — 19 Jul 2026
Strong period. Envelope approaching weathertight and M&E first fix accelerating. Programme recovered to on-track and forecast completion pulled forward. New winter-weather risk logged as a precaution.
Highlights
Concerns
Coming Up
Cost Summary
Contract Value
£6,800,000
Spent to Date
£4,256,000
Forecast Total
£4,298,560
Contingency Left
£2,501,440
Risk Register (3 open)
| high | Cladding fire-safety documentation sign-off | open |
| medium | M&E riser coordination clashes | open |
| high | Winter weather impact on envelope programme | open |