Northlight Interiors
Update 3 · 1–7 Nov
Riverside Café fit-out
For Riverside Ltd
54%done+13% this update
Time: At risk· finishes Tue 8 Dec (Opening day)
The counter top arrives four days later than planned.
Cost: Within budget · One approved change of £180 for extra sockets.
Next: Decoration and lighting from Mon 16 Nov

This update
Update 3 · 1–7 NovPlastering done; the counter top arrives four days late
- Plastering and ceilings100%+60% (was 40%)
- Counter, kitchen and joinery15%+15% (was 0%)
Plastering and ceilings are finished and drying well. The damp patch behind the old bar came from a leaking overflow in the flat above: the landlord has fixed it and the wall is dry and plastered. The joiner measured up on Thursday, but the stone supplier has moved the counter top delivery back four days.
Next update
The kitchen extraction goes in on Monday and the counter base is built on site. We need your floor tile choice this week to keep the tiler booked.
We need 2 things from you
Answer by Thu 12 Nov · decoration and lighting starts Mon 16 Nov
Choose the floor tile finish
Samples of all three are on the counter in the café. They cost the same and take the same time to lay.
Matt terracotta
Included in the price
Honed grey stone
Included in the price
Patterned encaustic
Included in the price
Questions first? Ask Sam or call 0117 496 0123.
Due Sat 14 Nov
When is your wifi provider installing the line?
We need the date so the data cabling in the store room is ready before they come.
- Answered: Two extra double sockets behind the counter +£180 · approved by Anna Clarke
Photos
Where we are
54% complete
- Done
- Under way
- At risk
- Late
- Not started
- Strip-out and making good✓ Done
- First fix: electrics and plumbing✓ Done
- First fix inspection✓ Done
- Plastering and ceilings✓ Done
- Counter, kitchen and joineryAt risk · 15%15% done, about 27% expected by now · ends Mon 23 Nov
- Decoration and lightingStarts 16 Nov
- Opening dayTue 8 Dec · 30 days
Since last update
- Time: On track → At risk
- 1 new issue
- 1 issue resolved
- 2 new requests for you
Issues
Counter top delivery is four days later than planned· Open
We have moved the decorators forward so the opening date still holds.
Damp patch behind the old bar· Resolved
The landlord fixed the overflow. The wall is dry and plastered.
Talk to us
Sam Okafor
Project lead
0117 496 0123 · sam.okafor@example.com
Earlier updates (2)
Update 2 · 25–31 OctFirst fix passed inspection and plastering has started
On trackUpdate 1 · 18–24 OctStrip-out finished and first fix under way
On track
Questions
Can we see the counter before it is finished?
a***@example.com · Thu 5 Nov 08:40
Of course. The base goes in next week, and Thursday afternoon is a good time to come by.
Sam Okafor · Fri 6 Nov 10:15
Will the water feed for the coffee machine be ready before the machine is delivered?
t***@example.com · Thu 29 Oct 11:05
Yes. The feed and the drain are in and tested; we cap them off until the machine arrives.
Sam Okafor · Thu 29 Oct 14:30