Meridian Construction
At RiskPDF

Meridian Quarter — Phase 2

Northgate Estates plc · PM: Priya Anand · Target: 26 Aug 2026

Since 4 Jul 2026
Progress 55% (+7)·Schedule On Track (was At Risk)·Forecast pulled in 3 days·1 new risk

Total Progress

Completion to handover

55%

Envelope & Cladding — Phase 4/7

Enabling & Demolition

100%

Substructure

100%

Superstructure Frame

100%

Envelope & Cladding

60%

schedule

At Risk

budget

On Track

risk

At Risk

Key Dates

34days

Practical Completion

26 Aug 2026

Progress Trend

Timeline

Current Date: 23 JUL 2026
Today
Enabling & Demolition
COMPLETE
100%
Substructure
COMPLETE
100%
Superstructure Frame
COMPLETE
100%
Envelope & Cladding
IN PROGRESS 60%
60%
M&E Services
IN PROGRESS 25%
25%
Fit-out & Handover
UPCOMING
0%
Practical Completion
0%
Nov 25Aug 26

← swipe to scroll →

Latest Update

19 Jul 2026by Priya Anand

Strong period. Envelope approaching weathertight and M&E first fix accelerating. Programme recovered to on-track and forecast completion pulled forward. New winter-weather risk logged as a precaution.

Highlights

  • Envelope at 60% — weathertight in sight
  • Programme recovered to On Track
  • Forecast completion pulled forward

Concerns

  • Winter weather could affect remaining envelope works

Coming Up

  • Achieve weathertight on all elevations
  • Complete M&E first fix in envelope zones

Financials

Contract Value

£6,800,000

Spent to Date

£4,256,000

Forecast Total

£4,298,560

Contingency Left

£2,501,440

Risk Register

3 open
high

Cladding fire-safety documentation sign-off

compliance · open

medium

M&E riser coordination clashes

technical · open

high

Winter weather impact on envelope programme

programme · open

Risk matrix — open risks

HML
Low impactMed impactHigh impact
1
1
1
↑ Likelihood

Site Photos

No site photos uploaded yet.

Update History

4 Jul 2026

Envelope now over halfway. M&E first fix underway in completed zones. Cladding fire-safety documentation flagged as a watch item.

Overall Progress48%
Schedule: At Risk
Budget: On Track
Risk: At Risk
Spend to date£3,264,000
17 Jun 2026

Frame topped out. Envelope installation commenced on the north elevation. M&E design coordination ongoing ahead of first fix.

Overall Progress42%
Schedule: At Risk
Budget: On Track
Risk: At Risk
Spend to date£2,856,000
27 May 2026

Superstructure frame progressing well. Envelope package procured and mobilising. Some early slippage on frame recovered through weekend working.

Overall Progress30%
Schedule: At Risk
Budget: On Track
Risk: At Risk
Spend to date£2,040,000

Status

At Risk

Days Elapsed

241

of 275 days planned

Budget Used

£4,256,000

of £6,800,000

Open Risks

3

2 critical/high

Cost Performance

1.14

Under budget

Download PDF Report