This is an example client page — answers and questions are switched off.

Northlight Interiors

Update 1 · 18–24 Oct

Riverside Café fit-out

For Riverside Ltd

33%done

Time: On track· finishes Tue 8 Dec (Opening day)

Cost: Within budget

Next: First fix inspection on Sun 25 Oct

See the full plan ›

This update

Update 1 · 18–24 Oct

Strip-out finished and first fix under way

The old bar, seating and ceiling tiles are out and the walls have been made good. The electricians started first fix on Tuesday: the new circuits for the kitchen and the coffee station are in, and the plumber has run the water feed to where the counter will stand.

Next update

First fix finishes and building control inspect it. Plastering starts straight after.

Where we are

33% complete

  • Done
  • Under way
  • At risk
  • Late
  • Not started
  1. Strip-out and making good✓ Done
  2. First fix: electrics and plumbingLate · 1 dayDue 23 Oct, 90% done
  3. First fix inspectionSun 25 Oct
  4. Plastering and ceilingsStarts 26 Oct
  5. Counter, kitchen and joineryStarts 1 Nov
  6. Decoration and lightingStarts 16 Nov
  7. Opening dayTue 8 Dec · 30 days
As of 24 Oct