Northlight Interiors

Update 2 · 25–31 Oct

Riverside Café fit-out

For Riverside Ltd

41%done+8% this update

Time: On track· finishes Tue 8 Dec (Opening day)

Cost: Within budget

Next: Counter, kitchen and joinery from Sun 1 Nov

See the full plan ›

This update

Update 2 · 25–31 Oct

First fix passed inspection and plastering has started

  • First fix: electrics and plumbing100%+10% (was 90%)
  • Plastering and ceilings40%+40% (was 0%)
  • First fix inspectionDone

Building control signed off the first fix on Monday with nothing to put right. The plasterers started on the back wall and the new ceiling is boarded over the seating area. With the walls open we found a damp patch behind where the old bar stood, so that wall will be plastered last.

Next update

Plastering and ceilings finish. The joiner measures up for the counter on Thursday.

Where we are

41% complete

  • Done
  • Under way
  • At risk
  • Late
  • Not started
  1. Strip-out and making good✓ Done
  2. First fix: electrics and plumbing✓ Done
  3. First fix inspection✓ Done
  4. Plastering and ceilings40% done
  5. Counter, kitchen and joineryStarts 1 Nov
  6. Decoration and lightingStarts 16 Nov
  7. Opening dayTue 8 Dec · 30 days
As of 31 Oct

Since last update

  • 1 new issue
  • 1 new request for you

Issues

  • Damp patch behind the old bar· Open

    The landlord's plumber is checking the flat above on Monday. We plaster that wall last.