Northlight Interiors
Update 2 · 25–31 Oct
Riverside Café fit-out
For Riverside Ltd
41%done+8% this update
Time: On track· finishes Tue 8 Dec (Opening day)
Cost: Within budget
Next: Counter, kitchen and joinery from Sun 1 Nov
See the full plan ›This update
Update 2 · 25–31 OctFirst fix passed inspection and plastering has started
- First fix: electrics and plumbing100%+10% (was 90%)
- Plastering and ceilings40%+40% (was 0%)
- First fix inspectionDone
Building control signed off the first fix on Monday with nothing to put right. The plasterers started on the back wall and the new ceiling is boarded over the seating area. With the walls open we found a damp patch behind where the old bar stood, so that wall will be plastered last.
Next update
Plastering and ceilings finish. The joiner measures up for the counter on Thursday.
Where we are
41% complete
- Done
- Under way
- At risk
- Late
- Not started
- Strip-out and making good✓ Done
- First fix: electrics and plumbing✓ Done
- First fix inspection✓ Done
- Plastering and ceilings40% done
- Counter, kitchen and joineryStarts 1 Nov
- Decoration and lightingStarts 16 Nov
- Opening dayTue 8 Dec · 30 days
Since last update
- 1 new issue
- 1 new request for you
Issues
Damp patch behind the old bar· Open
The landlord's plumber is checking the flat above on Monday. We plaster that wall last.